Infrastructure Projects

Project Profile

Rehabilitation/Improvement of Level III Water System

Project Code: SBDP-2023-10-13-14-007-01

Gallery

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Details

Region: REGION X - NORTHERN MINDANAO

Province: BUKIDNON

City/Municipality: MANOLO FORTICH

Location: So.Upper, So.Kihan-ay and Consolation, Guilang-Guilang, Manolo Fortich, Bukidnon

Funding Year: 2023

Date Started: December 19, 2023

Appropriation: P 6,606,882.00

Contract Amount: P 6,555,871.00

Source of Fund: DILG - SBDP - 2023

Contractor: NGP CONSTRUCTION

Status: On-Going

In-charge: Michelle Dacar

Physical Accomplishment: 57.08%

Remarks
  • PMC Inspection - April 2, 2024
  • 30.15% - Physical Accomplishment as of April 2, 2024
  • The construction of a 1 unit - 5 cu.m ferrocement collector box at Sitio Upper is still ongoing with an approximate accomplishment of 85.00%
  • The construction of a 1 unit - 20 cu.m ferrocement collector box at Sitio Upper is still ongoing with an approximate accomplishment of 90.00%
  • Initial construction of a pump house and steel framing for the solar panels in Sitio Upper has been observed.
  • The construction of 2 units - 5 cu.m ferrocement collector box and 1 unit - 20 cu.m ferrocement collector box are still pending for implementation.
  • NIT conducted last April 16, 2024
  • Based on the NIT conducted on April 16, 2024, the actual accomplishment is 51.48% with a positive slippage of +9.08%.
  • PMC Inspection May 16, 2024
  • PMC Inspection conducted last May 16, 2024, based on the actual evaluation, the physical accomplishment rate of the project is 57.08% and variance of +12.48%